Mosaic Expects Hurricane Ida To Disrupt North A... Now
Following Hurricane Ida in 2021, The Mosaic Company projected a 300,000-tonne reduction in Q3 phosphate production due to damage at Louisiana facilities and logistical bottlenecks. Repairs at the affected sites were expected to take 8 to 9 weeks, with ongoing production impacts through the end of that year. Read the full release at The Mosaic Company investors.mosaicco.com.